Roadwork Disruption On A3 Until End Of May


Works due from 8th - 31st May

Roadworks will be causing disruption on the A3 West Hill between Haldon Road and The Tibbets Corner Gyratory. These works have been commissioned by Transport for London and are being completed by their contractors Ringway Jacobs. Works commenced on 08/05/12 and are scheduled to be completed on 31/05/12.

 

All works will take place between 2100 and 0500 Monday to Friday Only to minimise disruption to the borough network.

 

The schedule of the works is as follows:

 

Tuesday 8th May - South Westbound resurfacing between Haldon Road and West Hill Road. Full Closure of A3 West Hill and junctions of Haldon Road, Amerland Road, West Hill Road and Portinscale Road.

 

Wednesday 9th May - South Westbound resurfacing between West Hill Road and Lytton Grove. Full Closure of A3 West Hill and junctions of Keswick Road, Sutherland Grove and Lytton Grove.

 

Thursday 10th May - South Westbound resurfacing between Lytton Grove and OS 184 West Hill. Full Closure of A3 West Hill and junctions of Lytton Grove, Dromore Road and Putney Heath Lane

 

Friday 11th May - South Westbound resurfacing between 184 West Hill and 30m south of Beaumont Road. Full Closure of A3 West Hill and junction of Beaumont Road.

 

Monday 14th May - North Eastbound resurfacing between Colebrook Close and Putney Heath Lane. Full Closure of A3 West Hill and junction of Putney Heath Lane.

 

Tuesday 15th May - North Eastbound resurfacing between Putney Heath Lane and Lytton Grove. Full Closure of A3 West Hill and junctions of Lytton Grove, Dromore Road and Putney Heath Lane

 

Wednesday 16th May - North Eastbound resurfacing between Lytton Grove and Portinscale Road. Full Closure of A3 West Hill and junctions of Keswick Road, Sutherland Grove, Lytton Grove and Portinscale Road.

 

Thursday 17th May - North Eastbound resurfacing between Portinscale Road and Haldon Road. Full Closure of A3 West Hill and junctions of Haldon Road, Amerland Road, West Hill Road and Portinscale Road.

 

Friday 18th May & Monday 21st May - South Westbound resurfacing between 30m South of Beaumont Road and Tibbets Corner Slip Road. Lane Closures

 

Tuesday 22nd May - South Westbound resurfacing of Tibbets Corner Off Slip. Full Closure of Tibbets Corner Off Slip.

 

Wednesday 23rd May & Thursday 24th May - South Westbound resurfacing of A3 Kingston Road (Tibbets Corner Underpass). Closure of A3 Kingston Road South Westbound.

 

Friday 25th May & Monday 28th May - North Eastbound resurfacing of A3 Kingston Road (Tibbets Corner Underpass). Closure of A3 Kingston Road North Eastbound.

 

Tuesday 29th May - North Eastbound resurfacing of Tibbets Corner On Slip. Full Closure of Tibbets Corner On Slip.

 

Wednesday 30th May & Thursday 31st May - North Eastbound resurfacing between Tibbets Corner On Slip and Colebrook Close. Lane Closures.

 

A copy of this schedule of works and a map showing the extent of the works can be found in the lobby on the Ground Floor of the Town Hall Extension, Wandsworth High Street.

 


May 9, 2012