Longer working hours being considered at South Wimbledon crossroads
Gas network bosses are considering longer working times at a major South Wimbledon project after road closures have been causing significant delays to drivers and bus passengers.
The junction at Kingston and Merton Road outside South Wimbledon tube (pictured above) is set to be closed until April 12 while essential Southern Gas Network work is carried out.
The £417,000 project involves replacing old metal gas mains with a new plastic pipe, which will have an 80-year lifespan. Details about the project are on this link.
SGN staff have been working from 8am to 6pm on weekdays, so they do not cause too much disturbance to residents. But since the reports of traffic gridlock near the diversion route in Pelham Road, journeys of a few minutes taking more than an hour and buses not taking the agreed diversion, they were seen working on Saturday (January 25).
SGN have been asked to consider working longer hours - eg on Sundays and until 10pm each night, in order to speed up the completion of the project. South Wimbledon Councillor Nigel Benbow has put this to SGN and they are "looking into it".
Councillor Benbow and Wimbledon MP Stephen Hammond have already met with SGN representatives on the site.
Since the traffic problems developed, Merton Council has improved the signage, with details below.
There are many other roadworks in the SW19 area which are likely to cause some local delays, including the 12-week road closure at South Wimbledon. They are all detailed below:
A238 Kingston Road, Wimbledon
20 January - 12 April
Responsibility for these works
Information for Road Users
Location: |
A238 Kingston Road, Wimbledon |
Traffic lights, etc: |
Traffic control (multi-way signals) |
Gas network upgrade
We’re upgrading our network to ensure local homes and businesses continue to enjoy a safe and reliable gas supply for years to come.
Our project will start on Monday 13 January and last approximately 12 weeks. It will involve road and lane closures around our site to keep everyone safe.
29 January — 31 January
Delays likely - Contra-flow
Works location: Unknown
Works description: Install 7m of 1 way poly duct in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500291288000
A219 Gladstone Road, Wimbledon
29 January — 31 January
Delays possible - Some carriageway incursion
Works location: Unknown
Works description: Install 1m of 1 way poly duct in Carriageway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500291841803
20 January — 17 February
Delays likely - Lane closure
Works location: Unknown
Works description: 12 mtrs of 180mm road crossing (new lay) 37mtrs of 75mm in 8". Cut off 10" main from 15mm. Abandon 20mtrs of 10/8" mains. Complete all services. Complete all reinstatement.
Responsibility for works: SGN
Current status: Planned work about to start
Works reference: XW053W116378314-05055
26 January — 02 February
Delays likely - Traffic control (Stop/Go boards)
Works location: Unknown
Works description: Replace 1 jointbox frame and cover(s) (725mm x 225mm) in Footway
Responsibility for works: Openreach
Current status: Planned work about to start
Works reference: BC006TI001LC500289315202
January 31, 2020